Road Program
2026 Road Program presentation with Proposed Roads
Preliminary Long-Range Project Schedule
Project Schedule - Updated July 22, 2026
Impacted Resident Notification - Fairway Drive
***July 29, 2026 Updates***
Concrete demo and pour this week : Brookbend Ct, Clarendon Ct, Southridge Cir, then Lily Pond Ln
Mill & overlay the development between Edgewood Elementary and Silver Lake this week, then Lily Pond Ln
Proposed schedule is as follows
- Thursday 8/20 – Mill South Crescent Blvd & Kathryn Ct
- Friday 8/21 – Mill Southridge Circle & Brookbend Ct, Pave S Crescent Blvd & Kathryn Ct
- Monday 8/24 – Mill Clarendon Ct, Pave Southridge Circle & Brookbend Ct
- Tuesday 8/25 – Pave Clarendon Ct